Matakana Link Road - September footage

Matakana Coast App

Auckland Transport (AT)

21 September 2022, 8:09 PM

Matakana Link Road - September footage

Matakana Link Road - Project update


Construction works on the Matakana Road roundabout are 90% complete and traffic is flowing freely. Night works carried out last month meant work on the eastern side of the road could be completed.


The bus stop on the western side of the road has been moved, cycling paths are fully formed and mulching and planting continues.


A final layer of asphalt will be laid later in the month.

On Te Honohono ki Tai (Matakana Link Road) attention is focussed on finishing kerbs and channels (90% complete) and pouring footpaths and cycleways (70% complete).


Side barriers for the bridge are being cast offsite prior to installing, while drainage, road construction and landscaping works continue.


Latest drone footage: