Kaipara District Council
29 June 2025, 7:38 PM
Stage 1 of the development on Wood Street and Fagan Place is now complete, with the new carpark now open and being used. It provides around 76 new parking spots. Entry to the carpark is via Fagan Place.
With the first stage of Wood Street and surrounds revitalisation and stormwater works wrapped up, HEB are now cracking on with the next part of the works. This second stage will take approximately six weeks to complete.
At the old fire station site
HEB are working in the old fire station site and behind Brewed As. Access to the new back carpark and parking between the medical centre and Gringas is possible via Fagan Place. Please do not park in front of the temporary fencing as this may block accessways for the construction team.
On Wood Street
HEB will use a combination of daytime work and night works to complete both stormwater drainage and new kerbing and footpaths on the northern side of Wood Street, from Molesworth Drive to Fagan Place (outside Four Square, Allied service station and Mangawhai community opshop). Daytime work between 7.00am and 5.00pm will kick off from next week and night works will start in mid-July. Wood Street will remain open, and it will still be possible to access these businesses, but things might look a little bit different for a while with temporary fencing and road cones in place. During construction a new pedestrian accessway – clearly signposted – will be created to access the shops. Please move slowly and carefully around the area when walking, cycling and driving. If you are unsure about access, just ask one of the HEB team members or phone ahead and ask the businesses before visiting.
If you have any questions, email the project team at [email protected]
For more information about this project head to https://www.kaipara.govt.nz/woodstreet