26 June 2024, 6:45 PM
Remedial work on the Omaha Wharf starts this week and is expected to finish in late September.
Work takes place from Monday to Friday and should take 10 weeks but depends on the weather.
During stage 1, people can still use the jetty for about a month. The gangway will be removed for repairs and the pontoon closed.
During stage 2, the jetty will be closed for repairs and the pontoon relocated to replace the piles.
During the final two weeks of the project, the gangway and pontoon will be re-installed.
Boaties can access the boat ramp as it is open throughout.
The work involves repairing the jetty and pontoon, replacing pontoon piles, and refurbing the connecting gangway.