04 March 2023, 7:55 PM
The night works at the Southern Connection of the project are still progressing following the recent weather events. However, works were postponed due to the cyclone and because of this we have had to extend these works for a further week.
The full SH1 closures between Silverdale to Johnstones Hill Tunnels (JHT) will continue for the following dates. While the closure is in place, traffic will detour along Hibiscus Coast Highway (HCH). A stop/go operation will be in place on HCH to manage traffic safely, from 9pm to 5am.
• Sunday 5 to Thursday 9 March
• Sunday 12 to Thursday 16 March
• Sunday 19 to Thursday 23 March
These are very weather dependant, so timings may change at short notice.
While all efforts have been made to limit disruption to traffic flows, we encourage you to plan your journey over this time and check the Waka Kotahi Journey Planner before heading out https://www.journeys.nzta.govt.nz/